Design of roads and motorwayse
Location:
Principal:Ministry of Transport, Communication and Water Management, Szolnok Road Directorate
Year:1995
Revenue:
Length of the road section:14.8 km
Design speed: 100 km/h
Grade separated interchanges: 2
Total length of cycle track: 7 km
Earthwork: 3.2 million m3
Asphalt pavement: 157 000 m2
- Soil investigation
- Surveying
- Preliminary studies
- Environmental assessments
- Design for approval
- Specifications
- Tender documentation
- Construction supervision
Trunk road No. 4 has an important role in linking the capital city with the eastern part of the country. Implementation of the Szolnok by-pass became necessary because of the dynamically increasing traffic. At determining the alignment of the bypass road it was necessary to ensure harmony between the road network master plans and the development plans concerning the region.
The new alignment also collects the traffic of the industrial area situated on the southern district of the town, handling it outside the dwelling area. It also offers a new crossing over the Tisza river. Total length of the bridge – considering the flood zone as well – is 678 m, including a span of 120 m for the channel bridge. A new high water dam had to be designed over a length of 6.3 km under the scope of the same project.
The road section to bypass the city is to be implemented by three phases as a primary trunk road with two lanes, of which the busiest middle section was first opened to traffic. This section is 3,5 km long, and includes the new Tisza bridge with cycle tracks.